Development Phase Batch X

Reservoir size: 30 cum per schemes
Pipes length (Transmission + Distribution): 20 + 2300 m and Tap stands 28 in Sagardina WSSP
Pipes length (Transmission + Distribution): 20 + 1900 m and Tap stands 24 in Materiya WSSP
Pipes length (Transmission + Distribution): 20 + 1800 m and Tap stands 22 in Matiariya WSSP
Pipes length (Transmission + Distribution): 20 + 2000 m and Tap stands 19 in Rambasti WSSP
Program implemented in VDC Bhodaha 2, 3 & 7; Inarwasira 2 and Prastoka 4 of Bara District
Total Number of training: 43
One toilet per household in project area
Beneficiaries are
Sagardina Water Supply Project: Total HHs 159; Total Pop. 921 (M 473, F 456); Poor HHs 18 (Pop. 117)
Materiya WSSP: Total HHs 171; Total Pop. 943 (M 495, F 448); Poor HHs 146 (Pop. 801)
Matiariya WSSP: Total HHs 163; Total Pop. 875 (M 476, F 399); Poor HHs 59 (Pop. 293)
Rambasti WSSP: Total HHs 155; Total Pop. 891(M 471, F 420) ; Poor HHs 72 (Pop. 412)
i. Community Organization and Mobilization
ii. Collection of Baseline Information
iii. Health, Hygiene and Sanitation Program
iv. Sanitation Activities for ODF campaign
v. School WASH Program
vi. WTSS program/Jeevika Program
vii. Jagaran and Conflict Resolution Plan Preparation
viii. Scheme ESMF, Catchment Protection Plan and Water Safety Plan Preparation
ix. Scheme Layout Plan Preparation
x. Meeting to agree on CAP outputs
xi. Detail Survey and Design
xii. Compliance and Process Monitoring

Client: RWSSFDB
Work Started: June, 2016
Work to be Completed: February, 2017
Service Charge: NPR. 4,130,835.00